Machine M and Machine N working alone at their constant rates, non stop, produced 6000 and 8000 nails respectively. Did...
GMAT Data Sufficiency : (DS) Questions
Machine M and Machine N working alone at their constant rates, non stop, produced 6000 and 8000 nails respectively. Did machine M work longer than machine N?
- Machine N produces 2000 more nails than machine M in one hour when each machine work at its constant rate
- Machine N produces twice as much as machine M in one hour when each machine work at its constant rate
Understanding the Question
Let's understand what we're asking: Did machine M work longer than machine N?
Given Information
- Machine M produced 6,000 nails total
- Machine N produced 8,000 nails total
- Both machines work at constant rates
What We Need to Determine
We need to know if Machine M's working time > Machine N's working time.
Here's the key relationship: Working time = Total nails produced ÷ Production rate
So we're asking: Is \(\frac{6000}{\mathrm{M's\ rate}} > \frac{8000}{\mathrm{N's\ rate}}\)?
This is a yes/no question - we need to determine with certainty whether M worked longer or not.
Key Insight
Machine M made fewer nails (6,000 vs 8,000). This might suggest it worked less time. BUT if Machine M is significantly slower than N, it could still work longer despite making fewer nails. The answer depends entirely on how their production rates compare.
Analyzing Statement 1
Statement 1 tells us: Machine N produces 2,000 more nails than Machine M in one hour.
This gives us a fixed difference between their rates: \(\mathrm{N's\ rate} = \mathrm{M's\ rate} + 2000\) nails/hour.
Testing Different Scenarios
Let's test extreme cases to see if we always get the same answer:
Scenario 1: Very slow rates
- If M produces 100 nails/hour, then N produces 2,100 nails/hour
- M's time: \(6000 \div 100 = 60\) hours
- N's time: \(8000 \div 2100 \approx 3.8\) hours
- Result: M works much longer than N ✓
Scenario 2: Very fast rates
- If M produces 10,000 nails/hour, then N produces 12,000 nails/hour
- M's time: \(6000 \div 10000 = 0.6\) hours
- N's time: \(8000 \div 12000 \approx 0.67\) hours
- Result: N works longer than M ✗
Since different scenarios give different answers to our yes/no question, we cannot determine with certainty whether M worked longer than N.
Conclusion
Statement 1 is NOT sufficient.
This eliminates choices A and D.
Analyzing Statement 2
Now let's forget Statement 1 completely and analyze Statement 2 independently.
Statement 2 tells us: Machine N produces twice as much as Machine M in one hour.
This gives us a ratio: \(\mathrm{N's\ rate} = 2 \times \mathrm{M's\ rate}\).
Logical Analysis
Here's the elegant insight: If N is twice as fast as M, but N only made \(\frac{8000}{6000} = 1.33\times\) as many total nails, then N must have worked for less time than M.
Let's think about it this way:
- If M works for some time T and makes 6,000 nails
- At double the rate, N would make 12,000 nails in the same time T
- But N only made 8,000 nails (not 12,000)
- Therefore, N must have stopped working before time T
Quick Verification
Let's verify with any rate for M:
- If M's rate = 1,000 nails/hour, then N's rate = 2,000 nails/hour
- M's time: \(6000 \div 1000 = 6\) hours
- N's time: \(8000 \div 2000 = 4\) hours
- Result: M works longer ✓
No matter what M's actual rate is, this relationship always holds true: M worked longer than N.
[STOP - Sufficient!]
Conclusion
Statement 2 is sufficient to answer that yes, Machine M worked longer than Machine N.
This eliminates choices C and E.
The Answer: B
Statement 2 alone tells us definitively that Machine M worked longer than Machine N, while Statement 1 alone does not provide enough information.
Answer Choice B: "Statement 2 alone is sufficient, but Statement 1 alone is not sufficient."