Loading...
A certain assembly project requires the completion of each of 5 tasks. In the diagram, the tasks are represented by circles labeled A-E and the number above each circle represents the number of days needed to complete the task. Arrows indicate prerequisite tasks. For instance, the arrow from Task A to Task C indicates that Task A must be completed before Task C can be started. Unless otherwise prohibited by these constraints, several tasks can be worked on at the same time. The project is complete once all 5 tasks are completed. Use the drop-down menus to create the most accurate statements based on the information provided.
| Text Component | Literal Content | Simple Interpretation |
|---|---|---|
| Project Description | "an assembly project requires the completion of each of 5 tasks" | The project consists of 5 specific tasks. |
| Task Representation | "tasks are represented by circles labeled A–E" | Each task is labeled A, B, C, D, or E. |
| Task Duration | "the number above each circle represents the number of days needed to complete the task" | Each task has a known duration (in days). |
| Dependency Signaling | "arrows indicate prerequisite tasks" | Arrows show which tasks must be completed before others begin. |
| Dependency Example | "arrow from Task A to Task C indicates...A must be completed before C" | If there's an arrow from A to C, A comes first. |
| Parallelism Permission | "unless otherwise prohibited by these constraints, several tasks can be worked on at the same time" | Multiple tasks can be done together if dependencies allow. |
| Completion Condition | "the project is complete once all 5 tasks are completed" | All five tasks must be finished for the project to end. |
| Chart Component | What It Shows | What It Means |
|---|---|---|
| Nodes | Tasks A, B, C, D, E plus begin/end nodes | Total of 7 nodes; each task/node has defined position. |
| Task Durations | \(\mathrm{A=8, B=5, C=7, D=21, E=5}\) (days) | D is longest at 21 days. |
| Start Arrows | Arrows from 'begin' to A, C, D | Tasks A, C, and D can start immediately. |
| Dependency Arrows | \(\mathrm{A→B, A→C, D→E}\) | Task B and C must wait for A; E waits for D. |
| End Arrows | \(\mathrm{B→end, C→end, E→end}\) | Project finishes when each path leads to 'end'. |
| Path Structure | Multiple pathways (\(\mathrm{A→B, A→C, D→E}\)) | Shows possible parallel work and dependencies. |
The least number of days needed to complete the project is _______ days.
If the number of days needed to complete Task C is increased by 1 day, then the least number of days needed to complete the project _______.
The minimum time to complete the project is 26 days, determined by the critical path \(\mathrm{D→E}\). Even if Task C is extended by one day, the 26-day path \(\mathrm{(D→E)}\) remains the critical path, so the project completion time stays the same.
The two blanks are dependent: correctly identifying the critical path in question 1 is essential for understanding why a 1-day delay in Task C does not affect the project completion time in question 2.